Melamchi Project warns of filing case against Italian contractor at Singapore court

Melamchi Project warns of filing case against Italian contractor at Singapore court

Melamchi Project warns of filing case against Italian contractor at Singapore court

The Melamchi Water Supply Project says it will file a case against the contractor company of the project, CMC, at a court in Singapore.

The Secretary at Ministry of Water Supply and Sanitation, who also heads the project’s board of directors, has already given their approval for the same.

The company had started the construction in 2013. The Italian company, however, halted works time and again while asking for compensations frequently.

Talking to Onlinekhabar, Secretary at the Ministry, Krishna Raj BC said, “The note of dissent we have has given us the approval with an agreement in principle to file the case at Singapore court.”

The contractor company has been claiming of high cost and delay in construction due to the 2015 Gorkha earthquake. The company said that they had to cut through a hill in Sindhupalchok claiming a compensation of Rs 1.65 billion including fine in various other topics.

Besides these, the Italian construction company had also demanded that its term be extended by 570 days to complete the construction.

The project officers have rejected the claims.

Meanwhile, the committee formed to resolve the issue between both the parties, Dispute Adjudication Board, had discussed the same on Friday. But, no conclusion has been made yet.

Source: Onlinekhabar

Please follow and like us:

aishworya

Related Posts

Crackdown on contractors won’t stop despite Mahaseth’s assurance: Home Ministry 4 SHARES FacebookTwitterEmail Onlinekhabar L-R: Home Minister Ram Bahadur Thapa and Physical Infrastructure Minister Raghubir Mahaseth Kathmandu, June 18 The Ministry of Home Affairs says it will not stop the ongoing crackdown on underperforming and nonperforming contractors just because Minister for Physical Infrastructure and Transport Raghubir Mahaseth reportedly assured that no contractors would be arrested. Mahaseth allegedly told contractors that they could contact him if they faced any action from the Home authority so that he could protect them. But, Home Ministry’s spokesperson Ram Krishna Subedi says the ongoing action would not stop. Whereas Mahaseth has been claiming that the Home Ministry crossed its jurisdiction and entered his sector by launching the crackdown, the Home Ministry says the issue is directly associated with people’s safety and security. “Members of the public have told us that they have been facing problems, they are unsafe because of delay in infrastructure development,” Subedi says, “It is our responsibility to address people’s problems. We can take action to make concerned stakeholders responsible.” “It is not against any law. The administration has to solve people’s problems.” Published on June 18th, Monday, 2018 11:44 AM Download Onlinekhabar App. Android click here & IOS click here . Keep in touch with us on Facebook, Twitter & YouTube. Related News From the Kathmandu Press: Monday, June 18, 2018 Home Minister tells businesspersons to inform him about extortionists Victims want Sudheer Basnet arrested again, Home Minister assures justice Ministry of Home Affairs Ministry of Physical Infrastructure and Transport Raghubir Mahaseth Ram Bahadur Thapa No Comments Leave a Reply Your email address will not be published. Comment Name Email Website

leave a comment

Create Account



Log In Your Account